CGEWHO Greater Noida Project – Monthly Progress Report from 1st Mar 2020 to 31st July 2020
MONTHLY PROGRESS REPORT CGEWHO GREATER NOIDA PROJECT
CGEWHO, Gr. Noida Project, Progress Report No. 49 from 1st MAR-2020 to 31st JULY-2020
- PACKAGE-II
Contractor: M/S KANWARJI CONSTRUCTION COMPANY
S. NO. | DURATION | PARTICULARS |
1 | 22.03.2020 | National bandh due to Public Curfew |
2 | 23.03.2020 TO 31.03.2020 | National lockdown vide letter no: F.51/DGHS/PH- IV/COVID-19/2020/prsecyhfw/3064-3163 on dtd: 22.03.2020. |
3 | 01.04.2020 TO 08.05.2020. | National lock down. |
4 | D.M Noida letter no: 381/2020/CX-3 stating to take permission from OSD GNIDA in connection to start the construction activities for the project. | 03.05.2020. |
5 | Permission given by OSD GNIDA on | Dtd: 08.05.2020. |
6 | Work Resume on | Dtd: 09.05.2020. |
7 | 09.05.2020 TO 31.07.2020 | Labour force is low in strength and progress is slowly picking up |
8 | 28.07.2020 | Site Review Meeting & site visit Project Managers of CGEWHO and Architect representative, General Manager and Project Managers of RTA and Contractors of Packages -4,5 & 6. |
9 | 31.07.2020 | Site visit of Dir (Tech), General Manager, Project Managers of CGEWHO and Chief Architect, General Manager and Project Managers of RTA & Contractors of all Packages. |
NOTE: – BLOCK D-08 RELEASED ON DTD: 06.02.2020.
- Comparative Progress of Site works: –
PACKAGE-II | STATUS AS ON 31/07/2020 |
As on 29.02.2020.
Block D03 |
· Staircase-1 stone flooring completed from Stilt to Basement.
· Bedroom-1 floor tiling work completed from 1st to 14th floor. · Internal Door Shutters Painting work completed up to 14th floor. · Basement ceiling plaster in wing-1 completed. · Machine Room entry door fixed. · Machine Room staircase railing fixing completed. |
1.3.2020 to 21.3.2020 | · Shaft brick work at -750mm lvl completed. |
& After getting | · Visitors Room sunken filling work completed at stilt floor lvl. |
Permission from
OSD G. Noida dtd:08.05.2020 till 31.07.2020 |
· Stilt floor vdf flooring in wings-2 & 4 completed.
· Diverter fixing work completed from 1st to 14th floor. · Door frame paint completed from 1st to 14th floor. · Internal wiring work completed up to 14th floor. |
· Switch & Socket fixing completed up to 14th floor. | |
· Stilt floor plumbing shaft louvers fixing completed. | |
· Bracket fixing in lifts completed. | |
As on 29.02.2020.
Block D04 |
· Internal Door shutters fixing work completed at 14th floor.
· Internal door shutters painting work completed up to 14th floor. · Internal door frames beading fixing work completed from 6th to 14th floor. · S.S Railing fixing work in wings-3 & 4 completed up to 14th floor. · Stilt floor ceiling plaster completed in wings-2 & 3. · Stilt floor VDF flooring completed. · Machine Room entry MS door fixing completed. |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G. Noida dtd:08.05.2020 till 31.07.2020 |
· Stilt floor vdf flooring in wings-1,3 & 4 completed.
· Machine Room Ms door frame fixing completed. · Stilt floor plumbing shaft louvers fixing completed. · Machine Room staircase Railing fixing completed. · Lift Guide Rails fixing work completed. · Internal wiring work completed up to 8th floor. |
As on 29.02.2020.
Block D05 |
· Machine Room entry MS door fixing work completed.
· Stilt floor Ceiling plaster work completed. · Door frame beading fixing work completed up to 14th floor. · Internal Door shutters fixing work completed up to 14th floor. · 2nd coat Internal wall putty work completed up to 14th floor. · Internal 1st coat painting work completed up to 8th floor. · Staircase-2 stone flooring completed up to 14th floor. · Balcony SS Railing fixing work in wings-1 & 2 completed from 1st to 14th floor. · Balcony SS Railing work in wings-3 & 4 completed from 6th to 14th |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020 till 31.07.2020 |
· Stilt floor vdf flooring in wings-1,3 & 4 completed.
· Stilt floor plumbing shaft louvers fixing completed. · Balcony SS Top rail fixing work completed from 1st to 14th floor. · Door shutter paint completed from 1st to 14th floor. · 1st coat paint work completed up to 14th floor. · Lift Guide Rails fixing work completed. · Aluminum Door window frames fixing work 85% completed. · Aluminum Door window glass fixing work 45% completed. · Machine Room staircase Railing fixing completed. |
As on 29.02.2020.
Block D06 |
· Terrace Projection above Machine Room 100% casted.
· Brick coba at terrace floor in wings-3 & 4 completed. · Tiles flooring completed from 7th to 14th floor. · Tiles dado in Toilets completed from 11th to 14th floor. · Staircase-1 Ms Railing fixing work completed from Stilt to 14th floor and in Staicase-2 from 12th to 14th floor. · Aluminium louvers in Plumbing shafts fixing work completed from 4th floor to 14th floor. · GI piping work at terrace floor completed. |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020 till 31.07.2020 |
· Stilt floor shaft brick work completed.
· Lift well white wash work completed. · Staircases-1 & 2 stone flooring completed from Basement to 14th floor. · Balcony SS Railing fixing work 85% completed. · Wall putty work completed from 1st to 12th floor. · Main door fixing work completed from 1st to 7th floor. · Door frame beading fixing completed up to 3rd floor. · Aluminum door window frames fixing work 50% completed. · Aluminum door window glass fixing work 20% completed. · Internal 1st coat painting work completed from 1st to 6th floor. |
As on 29.02.2020.
Block D07 |
· Machine Room columns 100% casted.
· Brick work completed at 14th floor. · Internal door frames fixing work completed from 10th to 13th floor. · Balcony RCC wall casted up to 14th floor. |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G. Noida dtd:08.05.2020 till 31.07.2020 |
· Terrace floor lvl parapet slab 50% casted.
· Overhead water tank base slab casted. · Internal plaster work completed from 2nd to 13th floor lvl. · Internal plaster at 14th floor lvl is in progress. · Vertical CI piping work completed from 2nd to 9th floor. · Internal wall conduiting work completed from 9th to 14th floor. |
As on 29.02.2020.
Block D08 |
· Stilt floor Roof slab 100% casted.
· 1st floor columns 30 nos casted. Total (30/70). |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020 till 31.07.2020 |
· Balance 1st floor columns 40 nos. casted. (Total 100%).
· 1st floor Roof slab 100% casted. · 2nd floor columns 25 casted. (25/70). |
As on 29.02.2020.
Non-Tower |
· Basement Roof slab 1390 Sqm casted. (Total 84%).
· Basement ceiling plaster 1500 Sqm completed. (Total 75%). · Ramp-6 Stub columns casted. · Ramp-6 side wall Reinforcement work is in progress. · Ramp-5 shuttering work is in progress. · Basement firefighting work 10% completed. (Total 40%). · Basement water supply piping work 15% completed. (Total 70%). · 8 nos ventilation cut outs casted. · 7 nos ventilation cut outs brick work completed. · 5 nos ventilation cutout plaster work completed. · 900 Sqm APP membrane fixing work completed. |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020 till 31.07.2020 |
· Basement ceiling plaster 2500 Sqm completed. (Total 85 % completed).
· 1500 Sqm PCC at Basement floor lvl completed. (Total 75% completed). · Basement floor drain work 50 mtrs completed. (Total 350mtrs completed). · 5560 Sqm APP membrane fixing work completed. (Total 39%). · IGL Trench Brick work 90 mtrs front of blocks D-03 & D-04 completed. · Drain Brick work 350 mtrs completed at -750mm lvl. · 3100 Sqm Screeding work on Water proofing membrane completed. (Total 32% completed). · Ramp-5 base slab casted. |
As on 29.02.2020.
Retaining Wall & Boundary wall |
· Retaining wall-3 of length 170mtrs casted.
· Retaining wall waterproofing with kota stone is in progress. · Boundary wall up to plinth lvl of length 70 mtrs casted. |
1.3.2020 to
21.03.2020 & After getting Permission from OSD G. Noida dtd:08.05.2020 till 31.07.2020 |
· Retaining wall waterproofing with kota stone is in progress.
· Boundary wall casting work 95% completed. · Boundary wall brick work 87 mtr. completed. (77% completed.) |
- MATERIAL RECEIVED UPTO 31/07/2020
PARTICULARS | MAKE | QUANTITY |
STEEL (FE 500D) | JSW, RINL, TATA & SAIL | 6428.53 MT |
CEMENT P.P.C (53 GRADE) | SHREE | 82400 Bag |
COMMENTS