CGEWHO Greater Noida Project – Monthly Progress Report from 1st Mar 2020 to 31st July 2020

CGEWHO Greater Noida Project – Monthly Progress Report from 1st Mar 2020 to 31st July 2020

MONTHLY PROGRESS REPORT CGEWHO GREATER NOIDA PROJECT 

 CGEWHO, Gr. Noida Project, Progress Report No. 49 from 1st MAR-2020 to 31st   JULY-2020

  1.  PACKAGE-II

 Contractor: M/S KANWARJI CONSTRUCTION COMPANY

 

S. NO. DURATION PARTICULARS
1 22.03.2020 National bandh due to Public Curfew
2 23.03.2020 TO 31.03.2020 National lockdown vide letter no: F.51/DGHS/PH- IV/COVID-19/2020/prsecyhfw/3064-3163 on dtd: 22.03.2020.
3 01.04.2020 TO 08.05.2020. National lock down.
4 D.M Noida letter no: 381/2020/CX-3 stating to take permission from OSD GNIDA in connection to start the construction activities for the project. 03.05.2020.
5 Permission given by OSD GNIDA on Dtd: 08.05.2020.
6 Work Resume on Dtd: 09.05.2020.
7 09.05.2020 TO 31.07.2020 Labour force is low in strength and progress is slowly picking up
8 28.07.2020 Site Review Meeting & site visit Project Managers of CGEWHO and Architect representative, General Manager and Project Managers of RTA and Contractors of Packages -4,5 & 6.
9 31.07.2020 Site visit of Dir (Tech), General Manager, Project Managers of CGEWHO and Chief Architect, General Manager and Project Managers of RTA & Contractors of all Packages.

NOTE: – BLOCK D-08 RELEASED ON DTD: 06.02.2020. 

  • Comparative Progress of Site works: –
PACKAGE-II STATUS AS ON 31/07/2020
As on 29.02.2020.

Block D03

·         Staircase-1 stone flooring completed from Stilt to Basement.

·         Bedroom-1 floor tiling work completed from 1st to 14th floor.

·         Internal Door Shutters Painting work completed up to 14th floor.

·         Basement ceiling plaster in wing-1 completed.

·         Machine Room entry door fixed.

·         Machine Room staircase railing fixing completed.

1.3.2020 to 21.3.2020 ·         Shaft brick work at -750mm lvl completed.
& After getting ·         Visitors Room sunken filling work completed at stilt floor lvl.
Permission from

OSD G. Noida dtd:08.05.2020 till 31.07.2020

·         Stilt floor vdf flooring in wings-2 & 4 completed.

·         Diverter fixing work completed from 1st to 14th floor.

·         Door frame paint completed from 1st to 14th floor.

·         Internal wiring work completed up to 14th floor.

·         Switch & Socket fixing completed up to 14th floor.
·         Stilt floor plumbing shaft louvers fixing completed.
·           Bracket fixing in lifts completed.
As on 29.02.2020.

 

Block D04

·         Internal Door shutters fixing work completed at 14th floor.

·         Internal door shutters painting work completed up to 14th floor.

·         Internal door frames beading fixing work completed from 6th to 14th floor.

·         S.S Railing fixing work in wings-3 & 4 completed up to 14th floor.

·         Stilt floor ceiling plaster completed in wings-2 & 3.

·         Stilt floor VDF flooring completed.

·         Machine Room entry MS door fixing completed.

1.3.2020 to

21.03.2020 & After getting Permission from OSD G. Noida dtd:08.05.2020 till 31.07.2020

·         Stilt floor vdf flooring in wings-1,3 & 4 completed.

·         Machine Room Ms door frame fixing completed.

·         Stilt floor plumbing shaft louvers fixing completed.

·         Machine Room staircase Railing fixing completed.

·         Lift Guide Rails fixing work completed.

·         Internal wiring work completed up to 8th floor.

As on 29.02.2020.

Block D05

·         Machine Room entry MS door fixing work completed.

·         Stilt floor Ceiling plaster work completed.

·         Door frame beading fixing work completed up to 14th floor.

·         Internal Door shutters fixing work completed up to 14th floor.

·         2nd coat Internal wall putty work completed up to 14th floor.

·         Internal 1st coat painting work completed up to 8th floor.

·         Staircase-2 stone flooring completed up to 14th floor.

·         Balcony SS Railing fixing work in wings-1 & 2 completed from 1st to 14th floor.

·         Balcony SS Railing work in wings-3 & 4 completed from 6th to 14th

1.3.2020 to

21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020  till 31.07.2020

·         Stilt floor vdf flooring in wings-1,3 & 4 completed.

·         Stilt floor plumbing shaft louvers fixing completed.

·         Balcony SS Top rail fixing work completed from 1st to 14th floor.

·         Door shutter paint completed from 1st to 14th floor.

·         1st coat paint work completed up to 14th floor.

·         Lift Guide Rails fixing work completed.

·         Aluminum Door window frames fixing work 85% completed.

·         Aluminum Door window glass fixing work 45% completed.

·         Machine Room staircase Railing fixing completed.

As on 29.02.2020.

Block D06

·         Terrace Projection above Machine Room 100% casted.

·         Brick coba at terrace floor in wings-3 & 4 completed.

·         Tiles flooring completed from 7th to 14th floor.

·         Tiles dado in Toilets completed from 11th to 14th floor.

·         Staircase-1 Ms Railing fixing work completed from Stilt to 14th floor and in Staicase-2 from 12th to 14th floor.

·         Aluminium louvers in Plumbing shafts fixing work completed from 4th floor to 14th floor.

·         GI piping work at terrace floor completed.

1.3.2020 to

21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020  till 31.07.2020

·         Stilt floor shaft brick work completed.

·         Lift well white wash work completed.

·         Staircases-1 & 2 stone flooring completed from Basement to 14th floor.

·         Balcony SS Railing fixing work 85% completed.

·         Wall putty work completed from 1st to 12th floor.

·         Main door fixing work completed from 1st to 7th floor.

·         Door frame beading fixing completed up to 3rd floor.

·         Aluminum door window frames fixing work 50% completed.

·         Aluminum door window glass fixing work 20% completed.

·         Internal 1st coat painting work completed from 1st to 6th floor.

As on 29.02.2020.

Block D07

·         Machine Room columns 100% casted.

·         Brick work completed at 14th floor.

·         Internal door frames fixing work completed from 10th to 13th floor.

·         Balcony RCC wall casted up to 14th floor.

1.3.2020 to

21.03.2020 & After getting Permission from OSD G. Noida dtd:08.05.2020 till 31.07.2020

·         Terrace floor lvl parapet slab 50% casted.

·         Overhead water tank base slab casted.

·         Internal plaster work completed from 2nd to 13th floor lvl.

·         Internal plaster at 14th floor lvl is in progress.

·         Vertical CI piping work completed from 2nd to 9th floor.

·         Internal wall conduiting work completed from 9th to 14th floor.

As on 29.02.2020.

Block D08

·         Stilt floor Roof slab 100% casted.

·         1st floor columns 30 nos casted. Total (30/70).

1.3.2020 to

21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020  till 31.07.2020

·         Balance 1st floor columns 40 nos. casted. (Total 100%).

·         1st floor Roof slab 100% casted.

·         2nd floor columns 25 casted. (25/70).

As on 29.02.2020.

Non-Tower

·         Basement Roof slab 1390 Sqm casted. (Total 84%).

·         Basement ceiling plaster 1500 Sqm completed. (Total 75%).

·         Ramp-6 Stub columns casted.

·         Ramp-6 side wall Reinforcement work is in progress.

·         Ramp-5 shuttering work is in progress.

·         Basement firefighting work 10% completed. (Total 40%).

·         Basement water supply piping work 15% completed. (Total 70%).

·         8 nos ventilation cut outs casted.

·         7 nos ventilation cut outs brick work completed.

·         5 nos ventilation cutout plaster work completed.

·         900 Sqm APP membrane fixing work completed.

1.3.2020 to

21.03.2020 & After getting Permission from OSD G.Noida dtd:08.05.2020  till 31.07.2020

·         Basement ceiling plaster 2500 Sqm completed. (Total 85 % completed).

·         1500 Sqm PCC at Basement floor lvl completed. (Total 75% completed).

·         Basement floor drain work 50 mtrs completed. (Total 350mtrs completed).

·         5560 Sqm APP membrane fixing work completed. (Total 39%).

·         IGL Trench Brick work 90 mtrs front of blocks D-03 & D-04 completed.

·         Drain Brick work 350 mtrs completed at -750mm lvl.

·         3100 Sqm Screeding work on Water proofing membrane completed. (Total 32% completed).

·         Ramp-5 base slab casted.

As on 29.02.2020.

Retaining Wall & Boundary wall

·         Retaining wall-3 of length 170mtrs casted.

·         Retaining wall waterproofing with kota stone is in progress.

·         Boundary wall up to plinth lvl of length 70 mtrs casted.

1.3.2020 to

21.03.2020 & After getting Permission from OSD G. Noida dtd:08.05.2020 till 31.07.2020

·         Retaining wall waterproofing with kota stone is in progress.

·         Boundary wall casting work 95% completed.

·         Boundary wall brick work 87 mtr. completed. (77% completed.)

  • MATERIAL RECEIVED UPTO 31/07/2020

 

PARTICULARS MAKE QUANTITY
STEEL (FE 500D) JSW, RINL, TATA & SAIL 6428.53 MT
CEMENT P.P.C (53 GRADE) SHREE 82400 Bag

cgewho-greater-noida-project-monthly-progress-report

Source: Click here to view/download the PDF