Minimum Wages for Industrial Workers of Stone Mines w.e.f 1st October 2023- Revised VDA Order dated 26.09.2023

HomeWages

Minimum Wages for Industrial Workers of Stone Mines w.e.f 1st October 2023- Revised VDA Order dated 26.09.2023

Minimum Wages for Industrial Workers of Stone Mines w.e.f 1st October 2023- Revised VDA Order dated 26.09.2023 by Office of the Chief Labour Commissioner(C)

File No. 1/8/ (7)2023 LS-II
Government of India
Ministry of Labour & Employment
Office of the Chief Labour Commissioner(C)
New Delhi

Dated: 26/9/2023

O R D E R

In exercise of the powers conferred by Central Government vide Notification No. S.O. 189(E) dated 19th January, 2017 of the Ministry of Labour and Employment the undersigned hereby revise the rates of Variable Dearness Allowance on the basis of the average Consumer Price Index for Industrial workers reaching 385.97 from 378.58 as on 30.06.2023 (Base 2016=100) and thereby resulting in an increase of 7.39 points . The revised Variable Dearness Allowance as under shall be payable from 01.10.2023;-

Rates of VOA for employees employed in “STONE MINES” shall be as under:-

Item of work Rates of Variable Dearness Allowance as on 01.10.2023
1. Excavation & removal of over burden with 50 meters lead /1.5 meters lift. *

(i) Soft Soil

(ii) Soft Soil with rock

(iii) Rock

 

 

Rs.157

Rs.232

Rs.307

2. Removal and stacking of rejected stones with 50 metres lead/ 1.5 Metres lift. * Rs.125
3. Stone breaking or Stone Crushing for the Stone size of:-
1.0 inch to 1.5 inches Rs.930
Above 1.5 inches to 3.0 inches Rs.795
Above 3.0 inches to 5.0 inches Rs.469
Above 5.0 inches Rs.387

Previous: Revised VDA on Minimum Wages for Industrial Workers of Stone Mines w.e.f 1st April, 2023

revised-vda-on-minimum-wages-stone-minesTherefore, the minimum piece rate wages showing the basic and Variable Dearness Allowance payable w.e.f. 01.10.2023 to the employees employed in Stone Mines shall be as under:-

Category Basic Wages V.D.A. Total
1. Excavation & removal of over burden with 50 metres Lead/1.5 Metres lift.*
(i) Soft Soil Rs.351 + Rs.157 = Rs.508
(ii) Soft Soil with rock Rs.531 + Rs.232 = Rs.763
(iii) Rock Rs.703 + Rs.307 = Rs.1010
2. Removal and stacking of refected stones with 50 meters lead/ 1.5 meters lift.* Rs.283 + Rs.125 = Rs.408
3. Stone Breaking or Stone Crushing for stone size of category ** Basic Wages VDA Total
(i) 1.0 inch to 1.5 inches Rs.2171 + Rs.930 = Rs.3101
(ii) Above 1.5 inches to 3.0 inches Rs.1857 + Rs.795 = Rs.2652
(iii) Above 3.0 inches to 5.0 inches Rs.1088 + Rs,469 = Rs.1557
(iv) Above 5.0 inches Rs.893 + Rs.387 = Rs.1280

The workers employed on minimum guaranteed time rate of wages per day shall be entitled to time rate of minimum wages plus special allowance, if any, for unskilled category of above ground workers revised from time to time by the Central Government in respect of scheduled employment in stone mines.
* Per 2.831 cube meters (100 cubic feet)
** Per truck load of 5.662 cubic meters (200 cubic feet)